The new blast furnace with a volume of 5870 cubic metre was inaugurated by T. V. Narendran, CEO and managing director, Tata ...
The company commenced the Rs 27,000-crore second phase of expansion of its Kalinganagar project in Odisha in November 2018.
With the current expansion, Tata Steel's capacity across sites in Odisha is at 14.6 mt. In Jharkhand, Tata Steel's capacity ...
Bhubaneswar: Tata Steel Friday commissioned country’s largest blast furnace at its Kalinganagar plant, which will help ...
Tata Steel has expanded the crude steel capacity at its Odisha facility at an investment of Rs 27,000 crore, the company said on September 20. The steel major commissioned what would be India’s ...
The new blast furnace, with a volume of 5,870 m3, is equipped with state-of-the-art features for long campaign life and an ...
Tata Steel has announced a significant expansion of its Kalinganagar plant in Odisha, increasing its crude steel capacity ...
The Phase II expansion of the facility, which commenced commercial production in May 2016 is supported by a ₹27,000 crore ...
Tata Steel boosts Kalinganagar plant capacity to 8mtpa with India's largest blast furnace, investing Rs ₹27,000 crore for ...
Even as the company is on the verge of commissioning its expanded capacity in Kalinganagar, Tata Steel believes that the ...
Kalinganagar: Tata Steel on Friday commissioned India’s largest blast furnace at its plant facility at Kalinganagar in Odisha ...
Tata Steel has commissioned India's largest blast furnace at its Kalinganagar plant, boosting its steel production capacity ...